SOLUTIONS / DATA CENTER INTERCONNECTION

Data center interconnection with a battery.

For most data center projects, the interconnection date sets the schedule. Grid operators now ask large loads to ride through faults, limit power variation and ramp at a permitted rate. A battery run by the Battalion EMS addresses those conditions in the interconnection study and can move an approval forward.

01 / SCHEDULE RISK

The interconnection sets the schedule.

Grid operators require large computational loads to demonstrate ride-through capability before they connect. In ERCOT, NOGRR 282 has set ride-through requirements for large computational loads since August 1, 2026. Utilities add ramp and variability limits in the interconnection agreement, and ERCOT has proposed a power-variation limit. A site that arrives with a battery already in the power design, and a simulation showing it meets each condition, has fewer open questions in the study and a shorter path to approval.

The NOGRR 282 ride-through page covers the fault case and the power smoothing page the variation limit.

02 / RAMP RATE

Training starts at the permitted pace.

Ramp rate control limits the change in net site load in both directions, in configurable megawatts per minute, at each feeder and at the point of interconnection. When a training job starts or a site moves onto its generators, the load changes in seconds. The battery covers the difference while the grid draw moves at the agreed rate, then recharges within the same limits.

Ramp rate control also protects on-site generation on the medium-voltage bus. Reciprocating engines cannot ramp fast enough for AI loads and gas turbines are slower still. The battery handles the rate of change that the generators cannot.

03 / LIMITED GRID AND ON-SITE GENERATION

One EMS for the grid connection and the generators.

Increasingly, data centers supplement a limited grid connection with on-site generation. Battalion EMS optimizes the power flows across the grid connection, the generators and the battery: it holds the interconnection limits, dispatches generation when the load exceeds the connection, and minimizes battery wear while doing it. The same controller runs the smoothing and ride-through functions, so there is one set of priorities for the site rather than three devices arguing.

Where the connection allows it, the battery also earns against the bill: four coincident peak (4CP) and five coincident peak (5CP) charges, energy price spikes, demand response and wholesale market services. Those are covered on the coincident peak programs and behind-the-meter pages.

04 / GETTING STARTED

Start with a conversation.

Tell us about the site and what the utility is asking for. If you already have a single-line diagram, a load profile or the utility’s draft conditions, they help us get specific sooner, and we can simulate the site and show how the controls meet each condition. Request information to start.

YOUR PROJECT

Request information

Tell us what you are evaluating. An engineer will review your request.

Use your company domain. Personal email providers are not accepted.

By submitting, you agree that Battalion may contact you about this request.