Battery-based uninterruptible power supply (UPS) at medium voltage, built for AI data centers. Dual conversion can replace the halls' low-voltage UPS. Parallel keeps the halls' UPS and generators, smooths the load pulses and restores the site's grid draw after a fault. Both run on one platform, controlled by Battalion EMS.
Interconnection, load pulses, generators and backup.
Interconnection. Grid operators now require large computational loads to stay connected through voltage and frequency disturbances. In ERCOT, Nodal Operating Guide Revision Request (NOGRR) 282, in force since August 1, 2026, sets voltage and frequency ride-through requirements for large computational loads: under Nodal Protocol Revision Request (NPRR) 1308, sites of 75 MW and above where at least half the demand is computational load. In dual conversion the battery carries the load through the disturbance. In parallel the halls’ own UPS carries the computers through a deep sag. In the scenario model, the blocks return the site’s draw to its pre-fault level within about one cycle of the voltage returning, up to the blocks’ rated power, well inside the 0.5 s NOGRR 282 allows. The interconnection study confirms the recovery for each site. The Battalion medium-voltage UPS is fully compatible with grid-fault ride-through interconnection rules such as ERCOT NOGRR 282, and the site study confirms the settings for each interconnection.
AI load pulses. Graphics processing unit (GPU) and tensor processing unit (TPU) clusters can swing tens of percent of facility load in under a second, every 20 seconds or so, thousands of times a day. The UPS block meets the swing at the feeder, so the grid sees the slow average. The same control damps power oscillations between the load and the supply.
Ramp rate and generators. Reciprocating engines and gas turbines ramp over seconds to minutes, and fuel cells and small reactors ramp more slowly still. The load moves in under a second. The battery takes the fast part of the ramp. In parallel, the blocks protect prime movers that share their medium-voltage bus from the torsional stress of pulse loads: on-site prime generation, or medium-voltage standby generators. With dual conversion, generation upstream of the blocks sees the grid-side converters’ slow average.
Backup and cost. A dual-conversion block carries the load through a loss of supply with 0 ms transfer. In the distributed parallel concept, if a feeder breaker opens and stays open, grid-forming blocks form voltage and frequency for their feeder section within their rating and duration, the halls keep running, and the existing generators remain the next layer. Capacity above the reserve lowers energy cost and demand charges where the tariff rewards it. These are secondary duties and never displace the reserve.
THE OFFERING
Parallel and dual conversion on one platform.
Battalion builds both parallel and dual-conversion medium-voltage UPS on one platform. The distribution, load tolerance and battery duty determine which connection the site needs.
Blocks are offered from 2.5 MW to 5 MW and above, in steps that include 3 MW, 3.5 MW and 3.75 MW, with durations from one to four hours and custom durations on request. The design is battery-system agnostic. Reference designs exist with validated battery and converter vendors, and a site can specify its own.
Fault tolerance is layered: N+1 at the block level, converter strings that fail one string at a time, paired controllers, redundant auxiliary power and a block that keeps running if the site network is lost. A dual-conversion block protects the hall from the grid and the grid from the hall. A parallel block protects the grid from the hall, and the halls’ own UPS protects the computers from grid sags.
Battalion is manufacturing medium-voltage UPS equipment for AI data center projects. The UPS is one offering within the Battalion platform, alongside the energy management system (EMS), remote operations and project modeling.
ONE BLOCK / DUAL CONVERSIONOne medium-voltage UPS block: hall transformer, load and grid converters, the Battalion control and aux power skid, battery containers and the ring main unit.
Dual conversion can replace the hall UPS. Parallel keeps it.
Dual conversion puts the block in series with the load. Each load section is always fed through its own load-side converter with 0 ms transfer, so the block can take the place of the halls’ low-voltage UPS. It can take the place of the standby generators only where the battery duration, 1 to 4 hours or custom on request, covers the site’s continuity requirement, which is the owner’s decision.
Parallel puts the blocks beside the load, on each medium-voltage feeder or at the substation bus. It is for a site that keeps its hall UPS and generators and must meet a ride-through rule such as ERCOT NOGRR 282 or a power-variation limit in its interconnection agreement, or that is planning for ERCOT’s proposed limit of 10 MW in any 5 seconds. The blocks smooth the load pulses at the grid connection and, sized for the hall load they back, return the site’s draw to its pre-fault level after a grid sag. They also protect generators that share their medium-voltage bus from the torsional stress of the pulses.
Dual conversion
Parallel
Position
Dual conversion sits in series with the load. The load-side converter feeds the hall, with the grid-side converter and the battery behind it on a shared direct-current connection.
Parallel blocks sit beside the load, on each medium-voltage feeder or at the substation bus. The feeder reaches the halls without passing through the blocks.
Hall UPS
Can be replaced. The load-side converter feeds the hall.
Kept in service.
Generators
Can be replaced only where the battery duration covers the site’s continuity requirement, which the owner sets. Otherwise kept.
Kept as the next layer of backup.
Transfer time
0 ms at the IT load.
Set by the halls’ own UPS.
IT load, deep sag
The load-side converter keeps forming the hall voltage from the battery. The IT load stays inside the ITIC curve, the industry curve for how long IT equipment survives a voltage deviation.
The halls’ own UPS carries the computers on its own batteries.
Grid side, deep sag
The grid-side converter limits its current or blocks.
The blocks stay connected and support the feeder voltage with reactive current. At 20 % voltage a block can exchange at most about 20 % of its rated power. The site’s draw falls, and falls further where a hall UPS moves its load onto its own batteries.
Voltage returns
The grid-side converter recovers. Scenario model of a 2.5 MW block through 500 ms at 20 % voltage: recovery begins at once and reaches 90 % 0.36 s after clearing.
In the scenario model, within about one cycle the blocks absorb power equal to the load the halls’ UPS still carries, up to the blocks’ rated power and with charge headroom held for it. The site’s draw is then back at its pre-fault level, well inside the 0.5 s NOGRR 282 allows. The interconnection study confirms the recovery for each site. The blocks reduce their charging as the hall UPS hands its load back, however long that takes.
Feeder lost
The load runs on the battery, with no transfer, for the duration the reserve allows.
In the distributed concept, grid-forming blocks form voltage and frequency for their feeder section within their rating and duration, and the halls keep running. The existing generators remain the next layer.
Load pulses
The load-side converters serve every pulse from the shared direct-current connection. The battery covers the difference and the grid-side converters follow a slow average.
The blocks inject and absorb the opposite of each pulse, with a 3 ms total response from measurement through command to the converter.
5 s variation
5.7 MW filtered and 6.6 MW raw at a simulated 1 GW campus running one training job, against ERCOT’s proposed 10 MW.
The same 5.7 MW filtered and 6.6 MW raw in the same 1 GW case.
Generators protected
Generation upstream of the blocks sees the grid-side converters’ slow average.
Generation that shares the blocks’ medium-voltage bus: on-site prime generation or medium-voltage standby generators. Low-voltage standby generators behind a hall’s own transfer switch are outside the blocks’ path once the hall transfers.
Redundancy
N+1 at the block level. The concept on a shared protected load bus is drawn with N+2, because a block loss there becomes a load step for the blocks that remain.
N+1 at the block level.
Concepts
Per load section, or on a shared protected bus.
Centralized at the substation, or distributed on each feeder.
The deep-sag rows describe a sag to 20 % voltage, as in the scenario model. In shallower sags the site study confirms how much power the site keeps drawing and how the blocks are sized for it.
Basis: the power variation readings come from one training job across a 1 GW campus of 600 MW of IT and 400 MW of cooling and mechanical load, with 50 ms of timing spread, on the published training shape of a GPU cluster (Choukse et al., arXiv 2508.14318, 2025). Both cases run in 1 ms steps with the production control code. The filtered reading uses the 0.1 to 55 Hz band named in the proposal, with filter corners that are our assumption, and the raw reading is unfiltered. The limit is one ERCOT has proposed and not yet adopted. The sag figures are a scenario model, and the interconnection study confirms the ride-through settings for each site.
PARALLEL / LOAD PULSE SMOOTHINGParallel blocks on one feeder section of a utility-scale AI campus. The campus load, grid draw and battery traces are the simulated 1 GW case above, played in real time.
PARALLEL / RIDE-THROUGHParallel blocks through a grid sag, shown slowed down. The halls’ own UPS carries the computers, the blocks support the feeder voltage, then restore the site’s draw once the voltage returns. A separate case shows the blocks forming the voltage for their section when the feeder stays open.
The two configurations can be combined on one site. The four connection concepts below show where each one connects, and the NOGRR 282 ride-through page walks through a grid fault in each.
CLASS VALUES
Class values for the medium-voltage UPS.
Item
Value
Basis
Voltage class
Medium voltage, up to 34.5 kV
Connection at the site distribution voltage
Block power
2.5 MW to 5 MW and above, in steps including 3 MW, 3.5 MW and 3.75 MW
Per UPS block
Duration
1 to 4 hours, custom on request
Set by the battery behind each block
Connection
Parallel or dual conversion
Chosen per site
Transfer time
0 ms on dual conversion
The load is always fed through its converter
Control
Decision in under 1 ms at 4,800 samples per second
UPS block controller. The EMS supervisory loop runs once per second
Availability
99.999 % design basis
System model with N+1 block failover, evaluated per site
Power variation
0.24 MW in 5 s at a 120 MW hall, 5.7 MW at a 1 GW campus running one training job, against ERCOT’s proposed 10 MW
Simulated on the published training-load shape at 1 ms, filtered 0.1 to 55 Hz as the proposal reads. Dual conversion at both sizes. Parallel blocks with a 3 ms total response read the same 5.7 MW at 1 GW
Grid-fault ride-through
Fully compatible with grid-fault ride-through interconnection rules such as ERCOT NOGRR 282.
Settings confirmed per site in the interconnection study
Battery
Battery-system agnostic
Reference designs with validated vendors
CONNECTION CONCEPTS
Four ways to connect the same building blocks.
Simplified concepts. The site sets the configuration.
BESS: battery energy storage system. PCS: power conversion system. RMU: ring main unit. STS: static transfer switch. DC: direct current.
01 / CONNECTION CONCEPT
Centralized parallel
One battery energy storage system (BESS) plant connects on dedicated feeders at the substation bus. Grid services act at the point of interconnection (POI). Loops and load stay unchanged. The plant is controlled at the common bus.
02 / CONNECTION CONCEPT
Distributed parallel
A BESS sub-block connects to each medium-voltage feeder through ring switchgear, also called a ring main unit (RMU). On feeder loss, the sub-block holds its section in grid-forming mode and the data halls stay on that section. Existing generators and transfer switches stay in place.
03 / CONNECTION CONCEPT
Dual conversion per load section
A power conversion system (PCS) faces the grid, a second PCS faces the load, and a battery connects to the direct-current (DC) bus between them. A static transfer switch (STS) connects to a backup bus. The racks see only the load PCS. Each load section has its own conversion equipment and backup transfer path.
04 / CONNECTION CONCEPT
Dual conversion on a shared protected bus
Grid PCS draw from the loop. Load PCS outputs are paralleled on a protected load bus, without static transfer switches. N+2 provides two blocks beyond the load requirement. A block loss becomes a load step on the remaining blocks, with no transfer time.
SHARED FOUNDATION
Local control in every block.
Each concept uses a medium-voltage PCS station, battery containers, ring switchgear, sub-block controllers in A/B pairs, an auxiliary power skid with two sources and a central energy management system (EMS). A module fault in a string PCS removes one string. The rest of the station remains available.
Every sub-block and block runs autonomously on loss of the EMS, the core network or the wide-area network (WAN).
Distribution, ride-through and duty set the choice.
Loop-fed sections with generator-backed pod feed units point to parallel. UPS-class isolation of the racks points to dual conversion. Hours of energy shifting point to parallel. Minutes of ride-through at full load point to dual conversion.
Combinations are possible. A site can use distributed parallel on the loops and dual conversion for one critical hall.
DESIGN BASIS
Availability design basis.
The availability model targets five nines (99.999 %) at the system level with N+1 block failover, one spare block beyond the load requirement. It is evaluated for each site.
String-level fault containment, paired controllers, redundant auxiliary power and block autonomy contribute to the system design. The dual-conversion concept on a shared protected load bus is drawn with N+2, two spare blocks, because the loss of a block there becomes a load step for the blocks that remain. Redundancy at each layer and the repair path are considered together.
GRID FUNCTIONS
Ride-through, power smoothing and ramp rate control.
The same block performs three grid-facing functions: it rides through a grid disturbance, it smooths load pulses, and it limits how fast the site’s grid draw can change. The AI data center solution describes each function and the simulation behind it.
OPERATION
Reserve for continuity. Dispatch around it.
Battalion EMS coordinates grid-facing power and the energy the load needs. State of charge (SOC) is the battery’s available charge as a percentage of its usable range. The required backup reserve remains a dispatch constraint.
Energy shifting, demand response and eligible market services use capacity above the reserve. Energence models the competing duties, battery life and warranty limits. Request an engineering review to compare the connection options against your single-line diagram.
Tell us what you are evaluating. An engineer will review your request.
Request information
Request received.
An engineer reviews every request and replies to approved company addresses within one business day.
Your email draft is ready. Send it to complete your request. If your mail client did not open, open the request email or email contact@battalion.energy from your company address with the same details.
We use analytics cookies to see how this site is used. Nothing is used for advertising. Privacy policy